In brief: in Italy, a company that entrusts works, services or supplies on its premises must check the contractor or self-employed worker before awarding the job. The law requires at least the chamber of commerce certificate and a self-declaration of the requirements (article 26 of Legislative Decree 81/2008), but after an accident what matters is whether the company was really suitable for that job: documents must be read against the risks, equipment and people involved. On construction sites, Annex XVII and the credit licence apply. Even with the help of a consultant, responsibility stays with the client.
What is technical and professional suitability (ITP)?
Idoneità tecnico-professionale (ITP) is defined in article 89(1)(l) of Legislative Decree 81/2008, written for construction sites but used as the reference for all contracts: having the organisational capacity, workforce, machinery and equipment needed for the work to be done. The duty to check it is set by article 26 for contracts within the company and by article 90 for construction sites.
Failing to carry out the check required by article 26 is punished with arrest from two to four months or a fine from €1,423.83 to €6,834.44 (article 55(5)(b)). After accidents, the Italian Supreme Court has repeatedly convicted clients who had not checked the company they chose.
Who must carry out the check
- Contracts within the company (Title I, article 26): the client employer. The check can be delegated under article 16 to a competent person, with a written and dated delegation accepted in writing and the necessary powers and budget; the employer must still supervise how the delegate performs it.
- Construction sites (Title IV, article 90): the client (committente, who is not necessarily an employer) or the responsabile dei lavori, if appointed, also when the works are entrusted to a single contractor or self-employed worker. The client is relieved only within the limits of the assignment (article 93).
- Subcontracts on site: the main contractor checks its subcontractors with the same criteria (Annex XVII, point 3).
The RSPP can help set up the procedure, but is not the person obliged to carry out the check.
What to ask for: the law and good practice
| Context | What the law requires (at least) | What is worth asking for |
|---|---|---|
| Works, services or supplies within the company (article 26) | Chamber of commerce registration certificate; self-declaration of the requirements (article 47 of Presidential Decree 445/2000); name of the preposto (paragraph 8-bis) | DURC; the relevant part of the contractor’s DVR; training and fitness certificates of the staff involved; list of vehicles and equipment; liability insurance |
| Construction site: main or executing contractor (article 90 and Annex XVII, point 1) | Chamber of commerce registration consistent with the contract; DVR; DURC; declaration of not being subject to suspension or prohibition measures (article 14); average annual workforce with INPS, INAIL and building fund registrations and the collective agreement applied (article 90(9)(b)); credit licence or SOA qualification class III or higher; for the main contractor, who performs the tasks of article 97 | Training and fitness certificates of site workers; equipment documentation; liability insurance |
| Construction site: self-employed worker (Annex XVII, point 2) | Chamber of commerce registration; conformity of machinery, equipment and temporary works; list of PPE; training and fitness certificates where required; DURC; credit licence | Liability insurance; experience on similar works |
| Construction site under 200 man-days without the particular risks of Annex XI (article 90(9)) | Chamber of commerce certificate, DURC and self-declaration on the other Annex XVII requirements; self-declaration on the collective agreement applied; credit licence | As above, in proportion to the risk |
| Subcontracts on site (Annex XVII, point 3) | The main contractor checks its subcontractors with the same criteria | Ask the main contractor for the outcome of its checks |
For works requiring a building permit or equivalent, before work starts the client or the responsabile dei lavori also sends the authorities a declaration that the documents have been checked (article 90(9)(c)). The POS is not proof of suitability: it is the contractor’s plan for that site, and the execution-phase coordinator checks it. More on when site rules apply in when Title IV applies.
Do contractors work on your premises in Italy?
We check the first three suppliers you name free of charge: you receive the outcome and a list of what is missing, with no commitment.
How to carry out the check: four steps
1. Define what the job requires. First establish whether it is a contract within the company (article 26) or a construction site, then what the contractor must be able to do: specific risks (work at height, confined spaces, electrical work), vehicles and equipment, training and qualifications, interference with your activities. This is the yardstick for reading the documents. For asbestos removal, the company must be registered with the national register of environmental operators and submit a work plan to the inspection authority.
2. Collect the documents listed in the table, according to the context.
3. Assess them on their merits: check that the documents match the work, look at technical and organisational skills (company profile, references for similar work, staff training) and at resources and equipment.
4. Monitor over time: compliance is not a one-off. Certificates, renewals and the DURC (valid for 120 days) expire; where possible, observe how the contractor works on site. The DURF, which concerns tax compliance in some contracts, is a different check from technical suitability.
Choosing the supplier and supervising the work
The check is not just collecting documents: their content must be assessed against the type and complexity of the work, to avoid liability for a wrong choice (culpa in eligendo). It also continues throughout the contractor’s activities, to avoid liability for lack of supervision (culpa in vigilando). During the work, supervision also goes through coordination: for contracts within the company through cooperation and the DUVRI, on construction sites through the execution-phase coordinator and the main contractor with its preposto.
This is why it helps to define a procedure for checking and managing contractors, a procedure for their access to the site, a digital system for their documents with reminders, and training for every department involved (purchasing, HR, RSPP, site management).
What Italian case law says
The Italian Supreme Court has returned to the client’s role several times. The duty to check arises even before the contract is signed, if the company starts working (Cass. pen. Sez. III n. 10014/2017, roof repair); a client who had not checked the contractor’s suitability was convicted of manslaughter (Cass. pen. Sez. IV n. 10544/2018); on construction sites it is not enough to rely on the contractor’s statements, documents must be produced and checked (Cass. pen. Sez. III n. 43604/2021). A formal check is not enough.
Software and outsourcing
A dedicated tool makes the check faster and easier to prove: suppliers upload their own documents, the platform tracks deadlines and sends reminders, and the history of checks is available in case of inspection. With SafetyoneClick, suppliers upload their documents, the platform flags missing or expired ones and, if the client wishes, Safetyone technicians review each document on its merits, normally within 48 working hours, and give reasons for every rejection. The responsibility stays with the client, but every request, outcome and deadline is recorded. The full set of client duties (risk information, DUVRI, safety costs, badges and preposto) is in our guide to article 26.
For foreign companies and start-ups in Italy
As clients, foreign groups with plants, warehouses or offices in Italy must run the check through the Italian employer, even when purchasing is centralised abroad: group supplier qualification helps, but the Italian documents (chamber of commerce certificate, self-declaration, DURC, staff training and fitness) must be collected and assessed for each contract. As contractors working for Italian clients, foreign companies are usually asked for the equivalent registration in their own country, a self-declaration of suitability, staff training and fitness records, ID badges, the name of their preposto and, on construction sites, the credit licence or an equivalent document. Our guide to health and safety law in Italy for foreign companies covers the other first steps.
Contractor suitability checks: frequently asked questions
Is the DURC enough to prove suitability?
No. It certifies social security compliance; suitability concerns organisation, people, equipment and skills for the specific work.
Can the check be delegated?
Yes, under article 16 with a formal delegation, or on construction sites by appointing a responsabile dei lavori; the client must still supervise.
Does the check have to be repeated?
Yes: documents expire and contracts change. The DURC is valid for 120 days, and staff training and fitness certificates have their own deadlines.
How many of your suppliers are compliant right now?
Safetyone Ingegneria Srl has worked in occupational health and safety since 2008: we check suppliers for clients across Italy with the SafetyoneClick platform, with a technician reviewing each document if you wish, in English if needed.
Want to see how this applies to your company? Let’s talk.
Marco Corazza, architect, founder of Safetyone and RSPP (health and safety advisor). In workplace safety since 1996.